IMPLEMENTATION PLAN
Resource Block Strategy:
- In the First Phase NRLM will be rolled out in 4 Resource Blocks namely: Siwan, Matanhail, Tauru and Bawani Khera
- HSRLM has signed MOU with SERP for Resource Block Strategy and for Training & Capacity Building.
- Blocks to be divided into clusters(2-4) depending upon the number of villages /low income families
- Each cluster will have one PRP and a team of 5 community resource persons
- Resource agency will depute experienced PRPs & CRPs to implement NRLM in Resource Blocks
- Develop internal CRPs with the help of Resource Agency
- SRLM staff to be trained by Resource Agency
- Training of PRIs, Bankers, local community leaders will be arranged through Resource Agency
- Two days Orientation Workshop for staff organized
Immersion Training of the First batch of staff - Feb. 12-26, 2013 organized. Second batch will be sent in June,2013.
Intensive Blocks Strategy:
- 12 Intensive Blocks including 4 resource blocks.
- Core Team in 8 blocks will be in place by Sep, 2013
- Orientation and Immersion Training of newly recruited staff by oct, 2013
- Mapping of SHGs in each block
- Training/Strengthening & CB of the Existing SHGs
- Exposure visits of the stake holders
- Focus on SHGs’ bank linkage
- Sensitization of bankers at block/district/state level
- Identification of internal CRPs & their capacity building
- Identification of Master Trainers for training
Non Intensive Blocks:
- Staff at state level is placed to look after this work
- Existing staff of DRDAs will be utilized wherever available
- Core team in the districts will be put in place by Sep, 2013 if DRDAs staff is not available.
- Training & Capacity Building of existing SGSY staff and SHGs
- Mapping of SHGs in each block
- Exposure Visits of stakeholders& SHGs members/ leaders
- Training /Capacity Building of SHGs
- Focus on SHGs’ bank linkage
- Sensitization of bankers at block/district/state level
- Identification of internal CRPs & their Capacity Building Identification of Master Trainers for various trainings
Phasing of Project Activities
| Phase | Year | Districts | Blocks |
|---|---|---|---|
| 1st | 1st (2013-14) | Bhiwani, Jhajjar, Kaithal and Mewat (4) | 12 Blocks |
| 2nd | 2nd (2014-15) | Bhiwani, Kaithal and Mewat. (3) Sonipat, Gurgaon, Y/Nagar, Hisar, Panipat, Rohtak, Karnal, M/garh and Fatehabad (9) | 30 Blocks |
| 3rd (2015-16) | Y/Nagar, Sonipat and Karnal (3) Rewari, Sirsa, Jind and Palwal (4) | 21 Blocks | |
| 4th (2016-17) | Rewari, Sirsa, Sonipat, Karnal, Jind, Palwal (6) Ambala (1) | 21 Blocks | |
| 3rd | 5th (2017-18) | Fatehabad, M/garh, Jhajjar, Hisar, Panipat, Bhiwani, Mewat, Kaithal, Gurgaon (9) Kurukshetra, Panchkula and (3) | 40 Blocks |
| Total | 21 | 124 |
Detail Of 1st Phase
| S No. | District | Block | BPL Families | Existing SHGs | Left Out BPL Families |
|---|---|---|---|---|---|
| 1 | Kaithal | Siwan* | 3737 | 237 | 1360 |
| Guhla | 7570 | 385 | 3720 | ||
| Rajond | 7513 | 271 | 4803 | ||
| 2 | Bhiwani | Bawani Khera* | 8077 | 166 | 6417 |
| Tosham | 8298 | 90 | 7398 | ||
| Bhiwani | 20362 | 360 | 16762 | ||
| 3 | Jhajjar | Matanhail* | 3344 | 76 | 2584 |
| Beri | 5102 | 70 | 4402 | ||
| Jhajjar | 9691 | 116 | 8531 | ||
| 4 | Mewat | Tauru* | 3583 | 206 | 1523 |
| Nagina | 7838 | 194 | 5898 | ||
| Nuh | 10167 | 346 | 6707 | ||
| Total | 4 | 12 | 95282 | 2517 | 70112 |
| *Resource Blocks Selected under NRLM | |||||







